The proposed Bell Center–Columbia–Sugar Creek–Illinois/Wisconsin State Line (BECI) Project is a major new infrastructure development that could significantly impact the agricultural landscape of southern Wisconsin. This $1.2 billion investment involves constructing approximately 190 miles of 765-kilovolt (kV) transmission lines connecting Crawford County to Walworth County before continuing to the state line. The project would also mark the first 765-kV transmission line constructed in Wisconsin, representing a significant increase in the scale of transmission infrastructure in the state.
Below is a map of the developer's preliminary study segments, not proposed or final routes. These segments are subject to change based on landowner input, engineering, surveys and studies.
765-kV Transmission Line Study Area
Project Timeline
*Timeframes are approximate and subject to change.
Late Summer 2026
Round 1 Public Open Houses and Community Engagement
Late Summer-Fall 2026
Route Development Continues
Late Fall 2026
Round 2 Public Open Houses and Community Engagement
Late Fall 2026
Refine and Finalize Routes
Early 2027
File Certificate of Public Convenience and Necessity with Public Service Commission of Wisconsin
Summer 2028
Anticipated PSCW Decision
Summer 2028-2029
Local and Federal Permitting
Summer 2028-Summer 2030
Easement Acquisition, Final Design and Surveys
Late 2029-Late 2033
Tree Clearing, Construction and Restoration
2033
Project in Service